Name of project : Resettlement areas Tay Do urban culture
Number : 05
Building location : County Cai Rang - Can Tho
Mission : create stable housing for people
Scope of works : - Works III - The area of 45 hectares land use - 43ha area of land for construction * Leveling: 43ha area * Road - trees, power supply - Lighting, water supply and drainage - Download 12T axle design - Hot Asphalt Pavement - Total length: 5.890m * Bridge Traffic - embankment - The design load for HL93 - Global Breadth: 45m - The length range needs: 260m - Reinforced concrete embankment: 850m - Embankment building stone: 1.688m
Capital investment : State Budget
Management Agency : Project Management Board to implement safety culture Tay Do
Total capital investment : - 356 billion VND , 823 million VND - Consulting Contract value : 443 million VND Consultant Scope : Survey - Design
Year : 2007
|